13.08.2012, 18:01 4675

Construction of aromatic hydrocarbon complex started at Atyrau Oil Refinery

General construction works such as pile driving, foundation seal, concreting foundation grills and foundations are currently underway at the construction sites, the Prime Minister's official website quotes the press service of the Ministry of Oil and Gas of Kazakhstan.

Almaty. August 13. Kazakhstan Today - Construction of an aromatic hydrocarbon production complex is underway at the Atyrau Oil Refinery, Kazakhstan Today reports.

General construction works such as pile driving, foundation seal, concreting foundation grills and foundations are currently underway at the construction sites, the Prime Minister's official website quotes the press service of the Ministry of Oil and Gas of Kazakhstan.

Besides, orders for supply of equipment including reactor units, compressors and others were submitted to producing plants.

To date, 948 equipment purchase agreements were signed. Totally, 1138 units of equipment will be procured.

This information may not be reproduced without reference to Kazakhstan Today. Copyright of materials of News Agency Kazakhstan Today.

Found an error in the text?

Select the error and press Ctrl + Enter at the same time.

relevant news

Most viewed