The discharge canal is 69% complete, while repairs on the Pervomaysky main canal have reached 66%. Construction of control checkpoints and the reservoir’s power supply system is 80% finished. We plan to complete all renovation work on the Kirov Reservoir by the end of this year," the Ministry of Water Resources and Irrigation reported.
As part of our Water Resources Management System Development Concept, the Ministry plans to carry out a comprehensive reconstruction of 37 reservoirs. Last year, we completed the first reconstruction of the Aktobe Reservoir in 36 years, which now has a capacity of 245 million cubic meters. Reconstruction of the Kapshagai reservoir in the Turkistan region is currently ongoing," said Deputy Minister of Water Resources and Irrigation Yerbolat Ibraikhanov.